ISLAND FIRE PROTECTION SOCIETY Emergency Services Buildings ESB #1 and ESB #2 - Project Budget and Actual Costs - |
||||||||||
As at June 11, 2011 | Budget | Actual | Difference | |||||||
Category | 3-May-10 | Costs | ||||||||
Site Selection | 2,726 | 2,726 | 0 | |||||||
Site Acquistion | 111,515 | 111,197 | 318 | |||||||
Architectural - design | 11,500 | 11,177 | 324 | |||||||
Engineering (inc. mezzanine) | 13,000 | 18,998 | (5,998) | |||||||
Engineering/geotech (prime design) | 3,381 | 3,764 | (383) | |||||||
Building Permit | 9,000 | 11,857 | (2,857) | |||||||
Survey, Legal, Zoning | 13,000 | 20,612 | (7,612) | |||||||
Appraisals | 4,900 | 4,361 | 539 | |||||||
Construction Insurance | 3,500 | 3,830 | (330) | |||||||
Temp Utilities | 2,500 | 2,500 | 0 | |||||||
Site Prep - clearing, excavation, fill | 96,000 | 110,547 | (14,547) | |||||||
Septic Tanks/ Connections | 15,000 | 13,696 | 1,304 | |||||||
Perimeter Drainage | 5,500 | 2,639 | 2,861 | |||||||
Concrete Footing, Foundation and Slab & Forms | 114,500 | 182,183 | (67,683) | |||||||
Structure Package | 256,000 | 260,082 | (4,082) | |||||||
Doors - interior | 6,000 | 6,553 | (553) | |||||||
Windows - interior | 2,000 | 0 | 2,000 | |||||||
Insulation - interior | 5,000 | 10,290 | (5,290) | |||||||
Exterior Enhancements | 20,000 | 0 | 20,000 | |||||||
Plumbing | 27,000 | 34,156 | (7,156) | |||||||
Electrical, Heating & Lighting | 82,500 | 96,948 | (14,448) | |||||||
HVAC/Mechanical | 70,000 | 36,286 | 33,714 | |||||||
Drywall | 47,000 | 51,112 | (4,112) | |||||||
Wood framing interior | 64,000 | 55,451 | 8,549 | |||||||
Cabinets/Shelving | 17,000 | 20,933 | (3,933) | |||||||
Millwork | 10,000 | 10,349 | (349) | |||||||
Flooring | 12,000 | 18,834 | (6,834) | |||||||
Painting | 11,000 | 17,276 | (6,276) | |||||||
Clean up and Disposal | 5,500 | 5,365 | 135 | |||||||
Final Grading and Gravel | 12,000 | 29,068 | (17,068) | |||||||
Project Management | 35,000 | 13,346 | 21,654 | |||||||
Water catchment & storage | 30,000 | 30,000 | 0 | |||||||
Furniture, blinds, etc | 6,000 | 3,000 | 3,000 | |||||||
Safety equipment | 2,000 | 0 | 2,000 | |||||||
Tender advertising | 1,000 | 403 | 597 | |||||||
Signage | 4,000 | 4,000 | 0 | |||||||
Landscaping, paving entrance | 15,000 | 48,806 | (33,806) | |||||||
Printing Courier & Comm. | 1,560 | 126 | 1,434 | |||||||
Hydro connection | 1,100 | 863 | 237 | |||||||
Telephone installation | 3,300 | 2,534 | 766 | |||||||
Contingency | 116,500 | |||||||||
Total - Budget / Costs | 1,268,482 | 1,255,864 | 12,618 | |||||||
Summary | ||||||||||
Expenditures | ||||||||||
- Budget / Costs | 1,268,482 | 1,255,864 | ||||||||
Recoveries: | ||||||||||
- Contingency | 12,618 | |||||||||
- GST/HST Rebate | (65,500) | (72,220) | 6,720 | |||||||
- Leased Space Modifications (est.) | (1,500) | 1,500 | ||||||||
Net Total Costs | 1,202,982 | 1,182,144 | 20,838 | |||||||
Note: All costs for ESB #1 and ESB #2 are included in the totals above, including budgeted amounts for those categories remaining to be completed. Yet to be completed are: landscaping and signs, water catchment, blinds, flooring, painting, and antenna tuning. GST/HST rebate includes actual amount for expenditures to-date plus an estimated amount related to categories not yet completed. | ||||||||||